Systems and methods for monitoring and controlling industrial processes
US-2024361756-A1 · Oct 31, 2024 · US
US9389607B2 · US · B2
| Field | Value |
|---|---|
| Publication number | US-9389607-B2 |
| Application number | US-201214122987-A |
| Country | US |
| Kind code | B2 |
| Filing date | Jun 18, 2012 |
| Priority date | Jun 24, 2011 |
| Publication date | Jul 12, 2016 |
| Grant date | Jul 12, 2016 |
A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
In a method for setting substrate-treatment time, substrate-treatment time is set by the following method. A predicted supply time of wafers of a following lot to a substrate processing apparatus is calculated based on a predicted plasma-treatment completion time of another substrate processing apparatus. A predicted plasma-treatment completion time of all of wafers of a present lot is calculated. A predicted idle time after the completion of the plasma treatment of all of the wafers of the present lot is calculated based on the predicted supply time of the following lot and the predicted plasma-treatment completion time of the present lot. If the predicted idle time is equal to or longer than the idle time required for dummy treatment, supplementary idle time is added between the plasma treatments of unprocessed wafers of the present lot.
Opening claim text (preview).
What is claimed is: 1. A method for setting substrate-treatment time in a substrate processing apparatus for performing predetermined treatment on substrates of a single lot one by one, the method comprising: a first calculation step of calculating predicted supply time of a second lot to the substrate processing apparatus, the second lot being supplied to the substrate processing apparatus after a first lot including a substrate that is currently subjected to the predetermined treatment in the substrate processing apparatus; a second calculation step of calculating predicted completion time of the predetermined treatment of all of the substrates of the first lot; a third calculation step of calculating predicted standby time after the completion of the predetermined treatment of all the substrates of the first lot in the substrate processing apparatus based on the calculated predicted supply time and the calculated predicted completion time; a determination step of determining whether or not the calculated predicted standby time is longer than a reference standby time required for dummy treatment; and an additional setting step of additionally setting, when the calculated predicted standby time longer than the reference standby time, supplementary standby time between the predetermined treatments of unprocessed substrates of the first lot. 2. The method of claim 1 , further comprising: another determination step of determining, in the case where the supplementary standby time is additionally set in the additional setting step, whether or not another standby time after the completion of the predetermined treatment of all the substrates of the first lot is longer than the reference standby time; and a deletion step of deleting, when said another standby time is longer than the reference standby time, the additionally set supplementary standby time. 3. The method of claim 1 , wherein each supplementary standby time has the same length. 4. The method of claim 1 , wherein when another predetermined treatment of a first substrate of the second lot is completed in another substrate processing apparatus, a predicted supply time of the second lot to the substrate processing apparatus is calculated by executing the first calculation step. 5. The method of claim 1 , wherein the supplementary standby time is shorter than the reference standby time. 6. A non-transitory computer readable storage medium storing a program for executing in a computer a method for setting substrate-treatment time in a substrate processing apparatus for performing predetermined treatment on substrates of a single lot one by one, wherein the method for setting substrate-treatment time comprises: a first calculation step of calculating predicted supply time of a second lot to the substrate processing apparatus, the second lot being supplied to the substrate processing apparatus after a first lot including a substrate that is currently subjected to the predetermined treatment in the substrate processing apparatus; a second calculation step of calculating predicted completion time of the predetermined treatment of all of the substrates of the first lot; a third calculation step of calculating predicted standby time after the completion of the predetermined treatment of all the substrates of the first lot in the substrate processing apparatus based on the calculated predicted supply time and the calculated predicted completion time; a determination step of determining whether or not the calculated predicted standby time longer than a reference standby time required for dummy treatment; and an additional setting step of additionally setting, when the calculated predicted standby time is equal to or longer than the reference standby time, supplementary standby time between the predetermined treatments of unprocessed substrates of the first lot. 7. The storage medium of claim 6 , wherein the method for setting substrate-treatment time further includes: another determining step of determining, in the case where the supplementary standby time is set in the additional setting step, whether or not another standby time after the completion of the predetermined treatment of all the substrates of the first lot is longer than the reference standby time; and a deletion step of deleting, when said another standby time is longer than the reference standby time, the additionally set supplementary standby time.
Cross-Sectional Technologies · mapped topic
Predict end of job execution, schedule new job beforehand · CPC title
Manufacturing semiconductor wafers · CPC title
characterised by job scheduling, process planning, material flow · CPC title
Production flow monitoring, e.g. for increasing throughput · CPC title