Method of stabilizing an electrical network by load shedding
US-2016315473-A1 · Oct 27, 2016 · US
US9954365B2 · US · B2
| Field | Value |
|---|---|
| Publication number | US-9954365-B2 |
| Application number | US-201514675030-A |
| Country | US |
| Kind code | B2 |
| Filing date | Mar 31, 2015 |
| Priority date | Jul 11, 2014 |
| Publication date | Apr 24, 2018 |
| Grant date | Apr 24, 2018 |
A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
This document relates to electricity management using modulated waveforms. One example modulates electricity to obtain modulated electricity having at least two different alternating current frequencies including a first alternating current frequency and a second alternating current frequency. The example delivers the modulated electrical power having the at least two different alternating current frequencies to multiple different electrical devices, including a first electrical device configured to utilize the first alternating current frequency and a second electrical device configured to utilize the second alternating current frequency. The modulated electricity can be delivered at least partly over an electrical line shared by the first electrical device and the second electrical device.
Opening claim text (preview).
The invention claimed is: 1. A system comprising: a filter configured to: receive modulated electricity having at least two different alternating current frequencies over an electrical line, the at least two different alternating current frequencies including a first alternating current frequency and a second alternating current frequency, and attenuate the second alternating current frequency of the modulated electricity to obtain filtered modulated electricity that is predominantly of the first alternating current frequency; and a meter configured to meter energy consumption at the first alternating current frequency separately from energy consumption at the second alternating current frequency. 2. The system of claim 1 , further comprising: a second filter configured to: receive the modulated electricity having the at least two different alternating current frequencies over the electrical line, and attenuate the first alternating current frequency of the modulated electricity to obtain second filtered modulated electricity that is predominantly of the second alternating current frequency; a first electrical device configured to operate on the filtered modulated electricity; and a second electrical device configured to operate on the second filtered modulated electricity. 3. The system of claim 2 , further comprising: a switch; and a processor configured to: receive an instruction to stop drawing power at the first alternating current frequency; and control the switch to stop the first electrical device from drawing power at the first alternating current frequency while the second electrical device continues to draw power at the second alternating current frequency. 4. The system of claim 3 , wherein the instruction is received over a computer network or over the electrical line. 5. The system of claim 2 , further comprising: another electrical line that carries the filtered modulated electricity to the first electrical device; and a further electrical line that carries the second filtered modulated electricity to the second electrical device. 6. The system of claim 5 , wherein the meter is deployed on the electrical line over which the modulated electricity is received. 7. The system of claim 5 , wherein the meter comprises a first meter deployed on the another electrical line and a second meter deployed on the further electrical line. 8. A method comprising: obtaining, on an electrical line, modulated electricity having at least two different alternating current frequencies including a first alternating current frequency and a second alternating current frequency; using a filter, attenuating the second alternating current frequency of the modulated electricity to obtain filtered modulated electricity that is predominantly of the first alternating current frequency; and using a meter, metering energy consumption at the first alternating current frequency separately from energy consumption at the second alternating current frequency. 9. The method claim 8 , further comprising: powering a first electrical device with the filtered modulated electricity that is predominantly of the first alternating current frequency. 10. The method of claim 9 , further comprising: using another filter, attenuating the first alternating current frequency of the modulated electricity to obtain second filtered modulated electricity that is predominantly of the second alternating current frequency; and powering a second electrical device with the second filtered modulated electricity that is predominantly of the second alternating current frequency. 11. The method of claim 10 , wherein the meter is placed on the electrical line and the electrical line carries the modulated electricity before the first alternating current frequency and the second alternating current frequency are attenuated. 12. The method of claim 10 , further comprising: metering the energy consumption using a first meter placed on another electrical line that carries the filtered modulated electricity and a second meter placed on a further electrical line that carries the second filtered modulated electricity. 13. The method of claim 10 , further comprising: modulating renewably-sourced energy at the first alternating current frequency; modulating fossil fuel-sourced energy at the second alternating current frequency; and providing the modulated electricity on the electrical line, the electrical line carrying both the renewably-sourced energy at the first alternating current frequency and the fossil fuel-sourced energy at the second alternating current frequency. 14. The method of claim 13 , further comprising: powering the first electrical device predominantly using the renewably-sourced energy, the first electrical device being powered by another electrical line carrying the filtered modulated electricity. 15. The method of claim 14 , further comprising: powering the second electrical device predominantly using the fossil fuel-sourced energy, the second electrical device being powered by a further electrical line carrying the second filtered modulated electricity. 16. The method of claim 15 , further comprising: sending an instruction over a network to control a switch, the instruction causing the switch to open and thereby prevent the second filtered modulated electricity from being provided to the second electrical device. 17. A system comprising: an electrical line configured to carry modulated electricity having at least two different alternating current frequencies including a first alternating current frequency and a second alternating current frequency; a meter configured to meter energy consumption at the first alternating current frequency separately from energy consumption at the second alternating current frequency; and a switch configured to control power consumption on the first alternating current frequency. 18. The system of claim 17 , further comprising: a computing device configured to power cap the first alternating current frequency separately from the second alternating current frequency by instructing the switch to open. 19. The system of claim 18 , wherein the computing device is further configured to: detect a shortage of power for an electrical grid carrying the modulated electricity; and instruct the switch to open responsive to detecting the shortage of power. 20. The system of claim 18 , further comprising: one or more first pieces of electrical equipment configured to draw current at the first alternating current frequency; and one or more second pieces of electrical equipment configured to draw current at the second alternating current frequency, the switch controlling power delivery to the one or more first pieces of electrical equipment. 21. The system of claim 20 , further comprising: a filter placed between the switch and the one or more first pieces of electrical equipment, the filter being configured to filter the modulated electricity to obtain first filtered electricity that is predominantly of the first alternating current frequency by attenuating the second alternating current frequency, the one or more first pieces of electrical equipment being powered by the first filtered electricity.
Home appliances · CPC title
using modification of a parameter of the network power signal · CPC title
using pulsed signals · CPC title
using the power network as support for the transmission · CPC title
the equipment forming part of substations · CPC title