Systems and methods for tethering subsea blowout preventers to enhance the strength and fatigue resistance of subsea wellheads and primary conductors
US-9359852-B2 · Jun 7, 2016 · US
US9919771B2 · US · B2
| Field | Value |
|---|---|
| Publication number | US-9919771-B2 |
| Application number | US-201514945094-A |
| Country | US |
| Kind code | B2 |
| Filing date | Nov 18, 2015 |
| Priority date | Nov 18, 2015 |
| Publication date | Mar 20, 2018 |
| Grant date | Mar 20, 2018 |
A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
A system and method for guiding a dropped suspended load includes a safety winch, safety buoy, and safety anchor spaced relative to one another and an offshore rig's lifting system so that the dropped load falls away from certain seabed locations and to a safe landing area. A safety winch cable runs from the safety winch to the safety buoy, and from the safety buoy to a connection to the load. The load, when in a run-away state, falls away from vertical and toward a predetermined safe landing spot on the seabed floor. The safety buoy is then used to locate the load.
Opening claim text (preview).
What is claimed: 1. A system comprising: a safety winch located on a drilling platform and including a safety winch cable; a safety buoy located in a body of water surrounding the drilling platform and including a cable spool; a safety buoy anchor located on a seabed of the body of water and including a safety buoy cable connecting the safety buoy to the safety buoy anchor; the safety winch cable running from the safety winch to the cable spool of the safety buoy and from the cable spool to a load to be lifted or lowered by a lifting system of the drilling platform different than that of the safety winch. 2. A system according to claim 1 further comprising a spacing between the safety buoy and the load being selected to provide a predetermined glide path for the load if the lifting system fails. 3. A system according to claim 1 further comprising a payout of the safety winch cable being in a synchronized relationship to a payout of the lifting system. 4. A system according to claim 1 further comprising the safety buoy being a water tight submergible safety buoy. 5. A system comprising: a safety winch arranged at a horizontal distance d 1 from a lifting system and having a safety winch cable; a safety buoy arranged at a horizontal distance d 2 from the safety winch and having means for changing a direction of the safety winch cable away from the safety buoy and toward a load to be lifted or lowered by the lifting system; and a safety buoy anchor arranged at a horizontal distance d 3 from the safety buoy and connected to the safety buoy by a safety buoy cable; the safety winch cable when in use running from the safety winch to the safety buoy and from the safety buoy to the load. 6. A system according to claim 5 further comprising the horizontal distance d 2 being a distance that provides a predetermined guide path of the load away from a vertical centerline of the lifting system when the load is in a dropped state. 7. A system according to claim 5 further comprising a payout of the safety winch cable being in a synchronized relationship to a payout of the lifting system. 8. A system according to claim 5 further comprising the safety buoy being a water tight submergible safety buoy. 9. A method for guiding a suspended load along a predetermined subsea guide path, the method including: routing a safety winch cable from a safety winch located on a drilling rig to a cable spool of safety buoy located in a body of water surrounding a perimeter of the drilling rig, and from the safety buoy to connection to a load to be suspended from a lifting system of the drilling rig different than that of the safety winch, wherein the safety buoy is anchored by a safety buoy anchor located on a seabed of the body of water. 10. A method according to claim 9 further comprising paying out the safety winch cable as the load is being lowered by the lifting system. 11. A method according to claim 10 further comprising synchronizing the paying out with that of the lifting system. 12. A method according to claim 9 further comprising braking a payout of the safety winch cable. 13. A method according to claim 9 further comprising using the safety buoy to locate the load when in a run-away state after being dropped by the lifting system.