Self-deploying telescoping jib crane system
US-10513214-B2 · Dec 24, 2019 · US
US2018361902A1 · US · A1
| Field | Value |
|---|---|
| Publication number | US-2018361902-A1 |
| Application number | US-201816113562-A |
| Country | US |
| Kind code | A1 |
| Filing date | Aug 27, 2018 |
| Priority date | Sep 25, 2014 |
| Publication date | Dec 20, 2018 |
| Grant date | — |
A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
A crane system includes a skid assembly having an operator base and plurality of outrigger assemblies coupled to the operator base that support and lift the base from a first elevation to a second elevation. The crane system also includes a jib crane coupled to the skid assembly. The jib crane includes a pillar assembly coupled to the skid assembly and a boom assembly coupled to the pillar assembly.
Opening claim text (preview).
What is claimed is: 1 . A method of loading a barrel onto a semi trailer, the method comprising: providing a crane assembly, the crane assembly including: a skid assembly having an operator base, the skid assembly further including a plurality of outrigger assemblies coupled to the operator base to support and lift the operator base from a first elevation to a second elevation, and a jib crane coupled to the skid assembly, the jib crane having a pillar assembly coupled to the skid assembly, and a boom assembly coupled to the pillar assembly; using the outrigger assemblies of the crane assembly to lift the operator base from a first elevation to a second elevation; moving a semi trailer underneath the operator base; engaging a hoisting component of the jib crane to a barrel; and moving the barrel onto the flatbed semi trailer. 2 . The method of claim 1 , wherein the operator base includes a lower plate, further comprising resting the lower plate on the semi trailer, such that the semi trailer provides at least partial vertical support for the operator base. 3 . The method of claim 1 , wherein the outrigger assemblies provide all vertical support for the operator base. 4 . The method of claim 1 , further comprising securing the skid assembly to the semi trailer using non-retractable twist lock mechanical engagements. 5 . The method of claim 1 , further comprising monitoring movement of the barrel with a plurality of cameras coupled to the crane assembly. 6 . The method of claim 1 , wherein the steps of engaging the hoisting component with the barrel and moving the barrel include telescopically extending and retracting the pillar assembly. 7 . The method of claim 1 , wherein the steps of engaging the hoisting component with the barrel and moving the barrel include telescopically extending and retracting the boom assembly. 8 . The method of claim 1 , wherein the step of moving the barrel includes lowering the barrel into a canister that is positioned on the semi trailer. 9 . The method of claim 8 , further comprising engaging the hoisting component of the jib crane to a canister lid, and moving the canister lid onto the canister after the barrel has been moved into the canister. 10 . The method of claim 1 , wherein the hoisting component includes a grapple, and wherein the step of engaging the hoisting component to the barrel includes coupling the grapple to the barrel. 11 . The method of claim 1 , wherein the semi trailer is a flatbed semi trailer, and wherein the barrel includes radiological material. 12 . A method of loading a barrel containing radiological material onto a flatbed semi trailer, the method comprising: providing a crane assembly, the crane assembly including: a skid assembly having an operator base, the skid assembly further including a plurality of outrigger assemblies coupled to the operator base to support and lift the operator base from a first elevation to a second elevation, a jib crane coupled to the skid assembly, the jib crane having a pillar assembly coupled to the skid assembly, a boom assembly coupled to the pillar assembly, and a hoisting component coupled to the boom assembly, and a plurality of cameras coupled to the jib crane; engaging the hoisting component to a barrel that contains radiological material; moving the barrel onto the flatbed semi trailer; and monitoring the movement with the plurality of cameras. 13 . The method of claim 12 , wherein at least one of the plurality of cameras is coupled to the pillar assembly. 14 . The method of claim 12 , wherein the steps of engaging the hoisting component with the barrel and moving the barrel include telescopically extending and retracting the pillar assembly. 15 . The method of claim 12 , wherein the steps of engaging the hoisting component with the barrel and moving the barrel include telescopically extending and retracting the boom assembly. 16 . The method of claim 12 , wherein the step of moving the barrel includes lowering the barrel into a canister that is positioned on the semi-trailer. 17 . The method of claim 16 , further comprising engaging the hoisting component of the jib crane to a canister lid, and moving the canister lid onto the canister after the barrel has been moved into the canister. 18 . The method of claim 12 , wherein the hoisting component includes a grapple, and wherein the step of engaging the hoisting component to the barrel includes coupling the grapple to the barrel. 19 . The method of claim 18 , wherein the grapple includes one of the plurality of cameras. 20 . The method of claim 12 , wherein the operator base includes a controller having a display, and wherein the step of monitoring the movement includes displaying feeds from the plurality of cameras on the display.
hydraulically actuated · CPC title
with jibs of adjustable configuration, e.g. foldable · CPC title
foldable or otherwise adjustable in configuration · CPC title
with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements · CPC title
Loading land vehicles {(loading or unloading boats to or from land vehicles B60P3/10)} · CPC title
Related publications grouped by family.
Answers are generated from the same data shown on this page.