Method for scheduling production on a continuous galvanizing line

US12371769B2 · US · B2

Patent metadata
FieldValue
Publication numberUS-12371769-B2
Application numberUS-202017776039-A
CountryUS
Kind codeB2
Filing dateNov 6, 2020
Priority dateNov 12, 2019
Publication dateJul 29, 2025
Grant dateJul 29, 2025

How to read this patent

A practical reading order for non-experts. Skip the full description unless you need deep technical detail.

  1. Title

    What the patent document calls the invention.

  2. Abstract

    A short plain-language summary of the technical disclosure.

  3. Assignees and inventors

    Who owns or filed the patent and who is credited as inventor.

  4. Key dates

    Filing, priority, publication, and grant dates set the timeline.

  5. First independent claim

    The legal scope of protection — read this for what is actually claimed.

  6. CPC / IPC classifications

    Technology tags used to group this patent with similar filings.

  7. Citations and related patents

    Prior art links and similar publications in this corpus.

Abstract

Official abstract text for this publication.

A method for setting the production schedule of a multiplicity of galvanized coils of metallic strip on a continuous galvanizing line is provided, the method including the steps of evaluating, for each possible combination of two uncoated coils, the impact of the transition from the first uncoated coil to the second uncoated coil on the quality of the galvanized coils, allocating to each possible combination of uncoated coils a weighting factor which depends on the results of the previous step and which takes into account the line constraints, computing the results of the previous step by calculating, for a number of possible schedules of the multiplicity of uncoated coils, a score which depends on the sum of the weighting factors attributed to the combinations of uncoated coils involved in the given schedule and by selecting the schedule with the optimal score.

First claim

Opening claim text (preview).

What is claimed is: 1. A method for setting a production schedule of a multiplicity of galvanized coils of metallic strip on a continuous galvanizing line having an annealing furnace, a zinc pot and a wiping machine, the method comprising the steps of: collecting a multiplicity of characteristics defining each uncoated coil to be galvanized, a multiplicity of specifications to be reached for each galvanized coil, a multiplicity of process parameters required to reach the specifications of each galvanized coil and a multiplicity of line constraints; evaluating, for each possible combination of two uncoated coils, an impact of the transition from the first uncoated coil to the second uncoated coil on a quality of the galvanized coils in relation to at least the following two sets of parameters: adjustment of temperature T p and speed S of the metallic strip in the annealing furnace, adjustment of pressure P of a wiping medium and distance D of the wiping machine from the metallic strip at an exit of the zinc pot; allocating to each possible combination of uncoated coils a weighting factor dependent on results of the evaluating step and taking into account the line constraints; computing the results of the allocating step by calculating, for a number of possible schedules of the multiplicity of uncoated coils, a score dependent on a sum of the weighting factors attributed to the combinations of uncoated coils involved in a given schedule and by selecting the schedule of the possible schedules with the optimal score; and galvanizing the uncoated coils of metallic strips on the continuous galvanizing line according to the schedule with the optimal score or according to an adjusted version of the schedule with the optimal score. 2. The method as recited in claim 1 wherein the multiplicity of characteristics defining each uncoated coil includes the thickness, the steel grade, the mechanical properties, the width and the hardness. 3. The method as recited in claim 1 wherein the multiplicity of specifications to be reached for each galvanized coil includes the zinc coating weight, the zinc coating weight tolerance, the occurrence of temper-rolling and the elongation to be reached during temper-rolling. 4. The method as recited in claim 1 wherein the multiplicity of process parameters required to reach the specifications of each galvanized coil includes the target temperature in the annealing furnace, the temperature tolerance in the annealing furnace, the line speed, the line speed tolerance in the annealing furnace, the wiping pressure P, the wiping distance D and the tension and force of the temper-rolling. 5. The method as recited in claim 1 wherein the multiplicity of line constraints includes the maximum capabilities of the line and transitions unauthorized by line operators. 6. The method as recited in claim 1 wherein, during the collecting step, the data are collected either manually or are obtained from an existing database or are computed. 7. The method as recited in claim 1 wherein the collecting step includes a modeling sub-step, at least part of the multiplicity of process parameters being calculated from empirical or physical or statistical laws or equations during the modeling sub-step. 8. The method as recited in claim 1 wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality in relation to one set of parameters is attributed a weighting coefficient. 9. The method as recited in claim 8 wherein, for each possible combination of two uncoated coils, the adjustment of the band temperature and speed in the annealing furnace is attributed the weighting coefficient, the weighting coefficient being dependent on a gap between the temperature tolerances of the two coils or on a gap between the speed tolerances of the two coils. 10. The method as recited in claim 8 wherein the weighting factor allocated to each possible combination of uncoated coils is the sum of the weighting coefficients attributed to the sets of parameters. 11. The method as recited in claim 1 wherein the continuous galvanizing line further includes a temper-rolling and wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality is further evaluated in relation to the adjustment of the tension T s and force F of the temper rolling. 12. The method as recited in claim 11 wherein, for each possible combination of two uncoated coils, the adjustment of the tension T s and force F of the temper rolling is attributed a weighting coefficient dependent on the line speed and the time needed to transition from one tension to another and/or from one pression to another. 13. The method as recited in claim 1 wherein the continuous galvanizing line further includes an entry accumulator and wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality is further evaluated in relation to the adjustment of the tension in the entry accumulator or in the annealing furnace. 14. The method as recited in claim 1 wherein the continuous galvanizing line further comprises a tension leveler and wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality is further evaluated in relation to the adjustment of the tension in the tension leveler. 15. The method as recited in claim 1 wherein the continuous galvanizing line further includes a galvannealing furnace and wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality is further evaluated in relation to the adjustment of the heating power in the galvannealing furnace. 16. The method as recited in claim 1 wherein the continuous galvanizing line further includes an oiling machine configured to apply oil on the galvanized coil and wherein the impact of the transition from the first uncoated coil to the second uncoated coil on the product quality is further evaluated in relation to the adjustment of an oil quantity or of an oil nature in the oiling machine. 17. The method as recited in claim 1 wherein the score calculated for a given schedule of the multiplicity of uncoated coils is the sum of the weighting factors attributed to the combinations of uncoated coils composing the schedule. 18. The method as recited in claim 1 wherein the score calculated for a given schedule of the multiplicity of uncoated coils includes sequence weighting terms in addition to the sum of the weighting factors attributed to the combinations of uncoated coils composing the schedule. 19. The method as recited in claim 1 further comprising the steps of: displaying the schedule with the optimal score and modifying it manually or automatically; and computing the score of the modified schedule. 20. A computer-readable medium storing computer program including software instructions, the software instructions when executed by a processor implementing the method as recited in claim 1 . 21. An electronic scheduling device for setting the production schedule of a multiplicity of galvanized coils of metallic strip on a continuous galvanizing line having an annealing furnace, a zinc pot and a wiping machine, the electronic monitoring device comprising: an acquisition module configured for collecting a multiplicity of characteristics defining each uncoated coil to be galvanized, a multiplicity of specifications to be reached for each galvanized coi

Assignees

Inventors

Classifications

  • C23C2/003Primary

    Apparatus · CPC title

  • characterised by the pre-treatment chambers located immediately upstream of the bath or occurring locally before the dipping process · CPC title

  • Scheduling, planning or task assignment for a person or group · CPC title

  • Computer-controlled implementation · CPC title

  • C23C2/0035Primary

    Means for continuously moving substrate through, into or out of the bath (C23C2/00344 takes precedence) · CPC title

Patent family

Related publications grouped by family.

External sources

Frequently asked questions

Answers are generated from the same data shown on this page.

What does patent US12371769B2 cover?
A method for setting the production schedule of a multiplicity of galvanized coils of metallic strip on a continuous galvanizing line is provided, the method including the steps of evaluating, for each possible combination of two uncoated coils, the impact of the transition from the first uncoated coil to the second uncoated coil on the quality of the galvanized coils, allocating to each possib…
Who is the assignee on this patent?
Arcelormittal
What technology area does this patent fall under?
Primary CPC classification C23C2/003. Mapped technology areas include Chemistry & Metallurgy.
When was this patent published?
Publication date Tue Jul 29 2025 00:00:00 GMT+0000 (Coordinated Universal Time) (B2). Legal status and post-grant events are not shown on this page.
What related patents are in patentsdb?
We list 1 related publication on this page (citations in our corpus or others sharing the same primary CPC).