Curtailed operation of a wind power plant by deactivation of wind turbines
US-2017321655-A1 · Nov 9, 2017 · US
US11536251B2 · US · B2
| Field | Value |
|---|---|
| Publication number | US-11536251-B2 |
| Application number | US-201917416968-A |
| Country | US |
| Kind code | B2 |
| Filing date | Dec 11, 2019 |
| Priority date | Dec 18, 2018 |
| Publication date | Dec 27, 2022 |
| Grant date | Dec 27, 2022 |
A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
The invention relates to a method for determining power set points of a power plant comprising a plurality of power generating units with at least one wind turbine generator. The determination of the power set points are based on a prioritization of the power generating units, where the power generating units are prioritized with respect to individual power levels or fatigue levels obtained for the power generating units. The prioritization is adjusted so that the adjusted prioritization depends both on the power and fatigue levels.
Opening claim text (preview).
The invention claimed is: 1. A method for controlling power generation from a power plant comprising a plurality of power generating units including at least one wind turbine generator, where the power plant is connected to an electrical power grid for supplying power from the power generating units to the electrical power grid, and where the power generating units are controllable to produce, dependent on individual power set points, power, the method comprises: for each power generating unit of the plurality of power generating units: (i) obtaining a fatigue level indicative of a combined accumulated fatigue level of one or more mechanical components of the power generating unit; and (ii) obtaining a power level indicative of the maximum power that can be produced by the power generating unit or indicative of the power produced by the power generating unit; determining a prioritized list of the plurality of power generating units wherein the plurality of power generating units are prioritized based on either the fatigue levels of the plurality of power generating units or the power levels of the plurality of power generating units; based on the plurality of power generating units being prioritized based on the fatigue levels of the plurality of power generating units, determining a first difference between the power level of a first power generating unit in the prioritized list and the power level of a second power generating unit located at a lower priority in the prioritized list than the first power generating unit; based on the plurality of power generating units being prioritized based on the power levels of the plurality of power generating units, determining a second difference between the fatigue level of the first power generating unit and the fatigue level of the second power generating unit; changing an order of the first power generating unit and the second power generating unit in the prioritized list based on the first difference or the second difference to produce an adjusted prioritized list; and determining power set points for a portion of the plurality of power generating units based on the prioritization of the plurality of power generating units in the adjusted prioritized list. 2. The method of claim 1 , where obtaining the power level comprises obtaining an available power level indicative of the maximum power that can be produced by the power generating unit, or obtaining an actual power level indicative of the power currently produced by the power generating unit. 3. The method of claim 2 , where the power set points have been determined based on using the available power level for the determination of the prioritized list or for the changing of the order. 4. The method of claim 1 , wherein the order of the first and second power generating units is changed based on the fatigue level of the second power generating unit indicating a lower fatigue than the fatigue level for of first power generating unit, or the power level of the second power generating unit being higher than the power level of the first power generating unit. 5. The method of claim 1 , comprising determining the prioritized list or changing the order in response to a change of a power reference. 6. The method of claim 1 , comprising determining if the prioritization will be performed dependent on the fatigue levels or the power levels based on an operating time of the power generating units. 7. The method of claim 1 , wherein the fatigue level for each of the power generating units is obtained based on a weighted sum of component fatigue levels of one or more mechanical components of each power generating unit. 8. The method of claim 1 , wherein the fatigue level is determined as a fatigue margin based on differences between component fatigue levels of one or more components and predetermined design fatigue limits of the one or more components. 9. The method of claim 1 , wherein the fatigue level for each power generating unit is weighted dependent on a rate of change of fatigue levels determined for one or more components. 10. A central controller for controlling power production of a power plant which comprises a plurality of power generating units including at least one wind turbine generator, where the power plant is connected to an electrical power grid for supplying power from the power generating units to the electrical power grid, and where at the central controller is arranged to dispatch individual power set points to the power generating units, and where the central controller is arranged to perform an operation, comprising: for each power generating unit of the plurality of power generating units: (i) obtaining a fatigue level indicative of a combined accumulated fatigue level of one or more mechanical components of the power generating unit; and (ii) obtaining a power level indicative of the maximum power that can be produced by the power generating unit or indicative of the power produced by the power generating unit; determining a prioritized list of the plurality of power generating units wherein the plurality of power generating units are prioritized based on either the fatigue levels of the plurality of power generating units or the power levels of the plurality of power generating units; based on the plurality of power generating units being prioritized based on the fatigue levels of the plurality of power generating units, determining a first difference between the power level of a first power generating unit in the prioritized list and the power level of a second power generating unit located at a lower priority in the prioritized list than the first power generating unit; based on the plurality of power generating units being prioritized based on the power levels of the plurality of power generating units, determining a second difference between the fatigue level of the first power generating unit and the fatigue level of the second power generating unit; changing an order of the first power generating unit and the second power generating unit in the prioritized list based on the first difference or the second difference to produce an adjusted prioritized list; and determining power set points for a portion of the plurality of power generating units based on the prioritization of the plurality of power generating units in the adjusted prioritized list. 11. The method of claim 2 , wherein the power set points have been determined based on using the actual power level for the determination of the prioritized list or for the changing of the order. 12. A computer program product comprising software code adapted to control a plurality of power generating units of a power plant when executed on a data processing system, the computer program product being adapted to perform an operation, comprising: for each power generating unit of the plurality of power generating units including at least one wind turbine generator: (i) obtaining a fatigue level indicative of a combined accumulated fatigue level of one or more mechanical components of the power generating unit; and (ii) obtaining a power level indicative of the maximum power that can be produced by the power generating unit or indicative of the power produced by the power generating unit; determining a prioritized list of the plurality of power generating units wherein the plurality of power generating units are prioritized based on either the fatigue levels of the plurality of power generating units or the power levels of the plurality of power generating units; based on the plurality of power generating units being prioritized based on the fatigue levels of the plurality of power generating units, deter
Maximum loads or fatigue criteria · CPC title
Wind turbines with rotation axis in wind direction · CPC title
Power (if explicitly mentioned) · CPC title
to prolong engine life · CPC title
controlling wind farms · CPC title
Related publications grouped by family.
Answers are generated from the same data shown on this page.