A practical reading order for non-experts. Skip the full description unless you need deep technical detail.
What the patent document calls the invention.
A short plain-language summary of the technical disclosure.
Who owns or filed the patent and who is credited as inventor.
Filing, priority, publication, and grant dates set the timeline.
The legal scope of protection — read this for what is actually claimed.
Technology tags used to group this patent with similar filings.
Prior art links and similar publications in this corpus.
Official abstract text for this publication.
Embodiments of the disclosure provide a method for controlling a power plant. The method may include detecting a transient load on the power plant, and monitoring a system reactance during operation at the transient load. A system reactance of the grid is compared with a switching threshold indicative of a switching event on the set of transmission lines. If the switching threshold is exceeded, the gas turbine operates at the transient load using a first control setting with a transient fuel management profile, a transient split bias profile, and a dynamic intake parameter for the gas turbine. If the switching threshold is not exceeded but one of the electrical properties exceeds a stability threshold, the gas turbine operates at the transient load using a second control setting with the dynamic intake parameter for the gas turbine, and without the transient fuel management profile or the transient split bias profile.
Opening claim text (preview).
What is claimed is: 1. A method for controlling a power plant having a generator mechanically coupled to a gas turbine through a shaft, the generator electrically coupled to a grid through a set of transmission lines, the method comprising: detecting a transient load on the power plant, based on electrical properties of the grid and electrical properties of the power plant, wherein the electrical properties of the grid include a system reactance of the grid; monitoring the system reactance of the grid via the generator during operation of the power plant at the transient load; determining whether the system reactance of the grid exceeds a switching threshold, the switching threshold being indicative of a switching event on the set of transmission lines; in response to the system reactance exceeding the switching threshold: operating the gas turbine at the transient load using a first control setting, the first control setting including a transient fuel management profile, a transient split bias profile, and a dynamic intake parameter for the gas turbine; and in response to the system reactance not exceeding the switching threshold, and one of the electrical properties of the power plant exceeding a stability threshold: operating the gas turbine at the transient load using a second control setting, the second control setting including the dynamic intake parameter for the gas turbine, wherein the second control setting does not include the transient fuel management profile or the transient split bias profile. 2. The method of claim 1 , wherein detecting the transient load includes detecting a load swing increase on the generator caused by an increase of operable transmission lines in the set of transmission lines, or by a reduction of operable transmission lines in the set of transmission lines. 3. The method of claim 1 , further comprising creating the first control setting and the second control setting based on a calculated difference between the system reactance and the switching threshold. 4. The method of claim 1 , wherein the dynamic intake parameter for the gas turbine does not affect a combustion parameter for a combustor of the gas turbine. 5. The method of claim 1 , wherein the dynamic intake parameter does not affect a split ratio between an air intake and a fuel intake of the power plant. 6. The method of claim 1 , wherein each of the first control setting and the second control setting are different from a non-transient control setting for operating the gas turbine at a non-transient load. 7. The method of claim 6 , further comprising operating the gas turbine at the non-transient control setting, while determining of whether the system reactance exceeds the switching threshold. 8. A program product stored on a computer readable storage medium for controlling a power plant having a generator mechanically coupled to a gas turbine through a shaft, and electrically coupled to a grid through a set of transmission lines, the computer readable storage medium comprising program code for causing a computer system to perform actions including: detecting a transient load on the power plant, based on electrical properties of the grid and electrical properties of the power plant, wherein the electrical properties of the grid include a system reactance of the grid; monitoring the system reactance of the grid via the generator during operation of the power plant at the transient load; determining whether the system reactance of the grid exceeds a switching threshold, the switching threshold being indicative of a switching event on the set of transmission lines; in response to the system reactance exceeding the switching threshold: operating the gas turbine at the transient load using a first control setting, the first control setting including a transient fuel management profile, a transient split bias profile, and a dynamic intake parameter for the gas turbine; and in response to the system reactance not exceeding the switching threshold, and one of the electrical properties of the power plant exceeding a stability threshold: operating the gas turbine at the transient load using a second control setting, the second control setting including the dynamic intake parameter for the gas turbine, wherein the second control setting does not include the transient fuel management profile or the transient split bias profile. 9. The program product of claim 8 , wherein detecting the transient load includes detecting a load swing increase on the generator caused by an increase of operable transmission lines in the set of transmission lines, or a reduction of operable transmission lines in the set of transmission lines. 10. The program product of claim 8 , further comprising creating the first control setting and the second control setting based on a calculated difference between the system reactance and the switching threshold. 11. The program product of claim 8 , wherein the dynamic intake parameter for the gas turbine does not affect a combustion parameter for a combustor of the gas turbine. 12. The program product of claim 8 , wherein the dynamic intake parameter does not affect a split ratio between an air intake and a fuel intake of the power plant. 13. The program product of claim 8 , wherein each of the first control setting and the second control setting are different from a non-transient control setting for operating the gas turbine at a non-transient load. 14. The program product of claim 13 , further comprising operating the gas turbine at the non-transient control setting, while determining of whether the system reactance exceeds the switching threshold. 15. A system comprising: a power plant having a generator mechanically coupled to a gas turbine through a shaft, and electrically coupled to a grid through a set of transmission lines; and a system controller in communication with the gas turbine of the power plant, the system controller being operable to: detect a transient load on the power plant, based on electrical properties of the grid and electrical properties of the power plant, wherein the electrical properties of the grid include a system reactance of the grid; monitor the system reactance of the grid via the generator during operation of the power plant at the transient load; determine whether the system reactance of the grid exceeds a switching threshold, the switching threshold being indicative of a switching event on the set of transmission lines; in response to the system reactance exceeding the switching threshold: operate the gas turbine at the transient load using a first control setting, the first control setting including a transient fuel management profile, a transient split bias profile, and a dynamic intake parameter for the gas turbine; and in response to the system reactance not exceeding the switching threshold, and one of the electrical properties of the power plant exceeding a stability threshold: operate the gas turbine at the transient load using a second control setting, the second control setting including the dynamic intake parameter for the gas turbine, wherein the second control setting does not include the transient fuel management profile or the transient split bias profile. 16. The system of claim 15 , wherein the system controller detecting the transient load includes detecting a load swing increase on the generator caused by an increase of operable transmission lines in the set of transmission lines, or by a reduction of operable transmission lines in the set of transmission lines. 17. The system of claim 15 , wherein the system con
for combustion engines · CPC title
for increasing the stability · CPC title
for limiting effects of transients · CPC title
electric · CPC title
Energy or water supply · CPC title