Method for low load operation of a power plant with a once-through boiler

US10196939B2 · US · B2

Patent metadata
FieldValue
Publication numberUS-10196939-B2
Application numberUS-201514807216-A
CountryUS
Kind codeB2
Filing dateJul 23, 2015
Priority dateJul 29, 2014
Publication dateFeb 5, 2019
Grant dateFeb 5, 2019

How to read this patent

A practical reading order for non-experts. Skip the full description unless you need deep technical detail.

  1. Title

    What the patent document calls the invention.

  2. Abstract

    A short plain-language summary of the technical disclosure.

  3. Assignees and inventors

    Who owns or filed the patent and who is credited as inventor.

  4. Key dates

    Filing, priority, publication, and grant dates set the timeline.

  5. First independent claim

    The legal scope of protection — read this for what is actually claimed.

  6. CPC / IPC classifications

    Technology tags used to group this patent with similar filings.

  7. Citations and related patents

    Prior art links and similar publications in this corpus.

Abstract

Official abstract text for this publication.

The once-through boiler includes a water supply and at least an economizer, an evaporator superheater. No valves are provided between the economizer, the evaporator and the superheater. The high-pressure turbine includes a control valve. The method for low load operation of a power plant with a once-through boiler and a high pressure turbine includes providing a parameter indicative of the stable operation of the once-through boiler in once-through operation, and on the basis of this parameter adjusting the control valve in order to regulate the pressure within the economizer and evaporator and/or adjusting the temperature of the water supplied to the economizer.

First claim

Opening claim text (preview).

The invention claimed is: 1. A method for low load operation of a power plant having a once-through boiler and at least one high pressure turbine, the once-through boiler having a water supply and an economizer, an evaporator and a superheater, the at least one high-pressure turbine comprising a control valve, the method comprising: providing at least one parameter indicative of stable operation of the once-through boiler in once-through operation, the at least one parameter obtained from a temperature and/or pressure measurement system and/or from a software model; and on the basis of the at least one parameter, (i) adjusting the control valve to regulate the pressure within the economizer and the evaporator and (ii) adjusting the temperature of the water supplied to the economizer, wherein low load is defined by a number of critical load values, and a number of partially open positions of the control valve are provided, each position being associated with a respective one of the number of critical load values, and when the load falls below a given load value of the number of critical load values, the method comprises adjusting the control valve to the partially open position associated with said given load value. 2. The method according to claim 1 , wherein the step of adjusting the control valve comprises partially closing the control valve. 3. The method of claim 1 , wherein the power plant further has an extraction line for supplying a part of steam discharged from the high-pressure turbine to a preheater for heating water supplied to an economizer, and the step of adjusting the temperature of the water supplied to the economizer further comprises regulating the pressure within the extraction line. 4. The method of claim 3 , wherein the extraction line has a regulation valve, and wherein regulating the pressure within the extraction line comprises adjusting the regulation valve. 5. The method of claim 3 , wherein the extraction line is connected to a source of high pressure fluid and regulating the pressure within the extraction line comprises adjusting the source of high pressure fluid. 6. The method of claim 1 , wherein the at least one parameter comprises at least a temperature measured at the evaporator and/or economizer. 7. The method of claim 1 , wherein the at least one parameter comprises a measured temperature spread between different tubes and/or tube bundles and/or tube sections of the evaporator and/or economizer. 8. The method of claim 6 , wherein the at least one parameter comprises measuring a measured temperature or plurality of temperatures over at least a tube of the evaporator and/or economizer at different measurement points on the tube and/or different radiuses of the tube wall. 9. The method of claim 6 , wherein the at least one parameter comprises a measured temperature fluctuation and/or temperature deviation of at least a tube of the evaporator and/or economizer over time. 10. The method of claim 1 , wherein adjusting the temperature comprises increasing the water temperature supplied to the economizer. 11. The method of claim 1 , wherein the once-through boiler has no valves between the economizer, the evaporator and the superheater.

Assignees

Inventors

Classifications

  • operating with superimposed recirculation during starting or low load periods, e.g. composite boilers (F22B35/125 takes precedence) · CPC title

  • of once-through type, i.e. built-up from tubes receiving water at one end and delivering superheated steam at the other end of the tubes (combined low- and high-pressure boilers of forced-flow type F22B33/16) · CPC title

  • F01K7/24Primary

    Control or safety means specially adapted therefor · CPC title

  • Control thereof · CPC title

  • F01K7/345Primary

    Control or safety-means particular thereto · CPC title

Patent family

Related publications grouped by family.

External sources

Frequently asked questions

Answers are generated from the same data shown on this page.

What does patent US10196939B2 cover?
The once-through boiler includes a water supply and at least an economizer, an evaporator superheater. No valves are provided between the economizer, the evaporator and the superheater. The high-pressure turbine includes a control valve. The method for low load operation of a power plant with a once-through boiler and a high pressure turbine includes providing a parameter indicative of the stab…
Who is the assignee on this patent?
Alstom Technology Ltd, General Electric Technology Gmbh
What technology area does this patent fall under?
Primary CPC classification F01K7/24. Mapped technology areas include Mechanical Engineering.
When was this patent published?
Publication date Tue Feb 05 2019 00:00:00 GMT+0000 (Coordinated Universal Time) (B2). Legal status and post-grant events are not shown on this page.
What related patents are in patentsdb?
We list 3 related publications on this page (citations in our corpus or others sharing the same primary CPC).