Participation factor based method for resynchronization of microgrids

US10044192B2 · US · B2

Patent metadata
FieldValue
Publication numberUS-10044192-B2
Application numberUS-201615017346-A
CountryUS
Kind codeB2
Filing dateFeb 5, 2016
Priority dateFeb 5, 2016
Publication dateAug 7, 2018
Grant dateAug 7, 2018

How to read this patent

A practical reading order for non-experts. Skip the full description unless you need deep technical detail.

  1. Title

    What the patent document calls the invention.

  2. Abstract

    A short plain-language summary of the technical disclosure.

  3. Assignees and inventors

    Who owns or filed the patent and who is credited as inventor.

  4. Key dates

    Filing, priority, publication, and grant dates set the timeline.

  5. First independent claim

    The legal scope of protection — read this for what is actually claimed.

  6. CPC / IPC classifications

    Technology tags used to group this patent with similar filings.

  7. Citations and related patents

    Prior art links and similar publications in this corpus.

Abstract

Official abstract text for this publication.

A microgrid is re-synchronized to a main grid or substation by determining a degree of bus angle or frequency mismatch and bus voltage mismatch between the microgrid and the main grid or substation prior to re-synchronization, determining an amount of power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below respective predetermined thresholds, determining at least one participation factor for each microgrid bus, each participation factor indicating an amount of influence power injection by the corresponding bus has on the bus angle or frequency mismatch or on the voltage mismatch, allocating the amount of power adjustment to the microgrid buses in proportion to the participation factors assigned to the buses, and re-synchronizing the microgrid to the main grid or substation responsive to the bus angle or frequency mismatch and bus voltage mismatch satisfying the respective predetermined thresholds.

First claim

Opening claim text (preview).

What is claimed is: 1. A method of re-synchronizing a microgrid to a main grid or substation, the microgrid including a plurality of buses to which energy resources and loads are connected, the method comprising: determining a degree of bus angle or frequency mismatch and bus voltage mismatch between the microgrid and the main grid or substation prior to re-synchronization; determining an amount of power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below respective predetermined thresholds; determining at least one participation factor for each of the buses, each participation factor indicating an amount of influence power injection by the corresponding bus has on the bus angle or frequency mismatch or on the voltage mismatch; allocating the amount of power adjustment to the buses in proportion to the participation factors assigned to the buses; and re-synchronizing the microgrid to the main grid or substation responsive to the bus angle or frequency mismatch and bus voltage mismatch satisfying the respective predetermined thresholds. 2. The method of claim 1 , wherein determining the amount of power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below the respective predetermined thresholds comprises determining an amount of real power adjustment and an amount of reactive power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below the respective predetermined thresholds. 3. The method of claim 2 , wherein determining at least one participation factor for each of the buses comprises: determining a first participation factor for each of the buses which indicates an amount of influence real power injection by the respective buses has on the bus angle or frequency mismatch; and determining a second participation factor for each of the buses which indicates an amount of influence reactive power injection by the respective buses has on the voltage mismatch. 4. The method of claim 3 , wherein allocating the amount of power adjustment to the buses in proportion to the participation factors assigned to the buses comprises: allocating the amount of real power adjustment to the buses in proportion to the first participation factors assigned to the buses; and allocating the amount of reactive power adjustment to the buses in proportion to the second participation factors assigned to the buses. 5. The method of claim 3 , wherein determining the first participation factor for each of the buses comprises: performing a singular value decomposition of a matrix that relates the amount of real power adjustment to the bus angle or frequency mismatch so as to yield a diagonal matrix having singular values which relate change in real power to change in bus angle or frequency for the buses; and determining the sensitivity of the largest singular value to variables associated with the buses. 6. The method of claim 5 , wherein the variables associated with the buses are the diagonal elements of the matrix that relates the amount of real power adjustment to the bus angle or frequency mismatch. 7. The method of claim 3 , wherein determining the second participation factor for each of the buses comprises: performing a singular value decomposition of a matrix that relates the amount of reactive power adjustment to the bus angle or frequency mismatch so as to yield a diagonal matrix having singular values which relate change in reactive power to change in bus angle or frequency for the buses; and determining the sensitivity of the largest singular value to variables associated with the buses. 8. The method of claim 7 , wherein the variables associated with the buses are the diagonal elements of the matrix that relates the amount of reactive power adjustment to the bus angle or frequency mismatch. 9. The method of claim 2 , further comprising: preventing one or more of the buses from contributing to the real power adjustment; and normalizing the participation factors so that the sum of the normalized participation factors for the buses allowed to contribute to the real power adjustment equals one. 10. The method of claim 2 , further comprising: preventing one or more of the buses from contributing to the reactive power adjustment; and normalizing the participation factors so that the sum of the normalized participation factors for the buses allowed to contribute to the reactive power adjustment equals one. 11. The method of claim 1 , wherein allocating the amount of power adjustment to the buses in proportion to the participation factors assigned to the buses comprises instructing the energy resources connected to the buses to adjust their operating set points in proportion to the participation factors assigned to the buses. 12. The method of claim 11 , further comprising: excluding one or more of the resources from being considered in determining the participation factors for the buses, responsive to the one or more resources operating at or close to its maximum operating set point limit. 13. The method of claim 11 , further comprising: shedding one or more of the loads so as to enter islanded mode in which the microgrid is disconnected from the main grid or substation, in accordance with the participation factors assigned to the buses. 14. A controller for a microgrid that includes a plurality of buses to which energy resources and loads are connected, the controller comprising a re-synchronization unit operable to: determine a degree of bus angle or frequency mismatch and bus voltage mismatch between the microgrid and the main grid or substation prior to re-synchronization; determine an amount of power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below respective predetermined thresholds; determine at least one participation factor for each of the buses, each participation factor indicating an amount of influence power injection by the corresponding bus has on the bus angle or frequency mismatch or on the voltage mismatch; allocate the amount of power adjustment to the buses in proportion to the participation factors assigned to the buses; and re-synchronize the microgrid to the main grid or substation responsive to the bus angle or frequency mismatch and bus voltage mismatch satisfying the respective predetermined thresholds. 15. The controller of claim 14 , wherein the re-synchronization unit is operable to determine an amount of real power adjustment and an amount of reactive power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below the respective predetermined thresholds. 16. The controller of claim 15 , wherein the re-synchronization unit is operable to determining a first participation factor for each of the buses which indicates an amount of influence real power injection by the respective buses has on the bus angle or frequency mismatch, and determine a second participation factor for each of the buses which indicates an amount of influence reactive power injection by the respective buses has on the voltage mismatch. 17. The controller of claim 16 , wherein the re-synchronization unit is operable to allocate the amount of real power adjustment to the buses in proportion to the first participation factors assigned to the buses, and allocate the amount of reactive power adjustment to the buses in proportion to the second participation factors assigned to the buses. 18. The controller of claim 16 , wherein the re-synchronizat

Assignees

Inventors

Classifications

Patent family

Related publications grouped by family.

External sources

Frequently asked questions

Answers are generated from the same data shown on this page.

What does patent US10044192B2 cover?
A microgrid is re-synchronized to a main grid or substation by determining a degree of bus angle or frequency mismatch and bus voltage mismatch between the microgrid and the main grid or substation prior to re-synchronization, determining an amount of power adjustment needed to reduce the bus angle or frequency mismatch and bus voltage mismatch to below respective predetermined thresholds, dete…
Who is the assignee on this patent?
Abb Technology Ltd, Abb Schweiz Ag
What technology area does this patent fall under?
Primary CPC classification H02J3/383. Mapped technology areas include Electricity.
When was this patent published?
Publication date Tue Aug 07 2018 00:00:00 GMT+0000 (Coordinated Universal Time) (B2). Legal status and post-grant events are not shown on this page.
What related patents are in patentsdb?
We list 3 related publications on this page (citations in our corpus or others sharing the same primary CPC).